The site assessment, test by test
Will a granny flat fit in your backyard?
Here is exactly what we check before we say yes.
Every E2ES assessment runs the same sequence on the same public data: the title boundary and easements from the Victorian cadastre, the existing house from the state building layer and current aerial imagery, then one of three fixed floor plans placed whole behind the house with the clearances the building and fire rules require, the trees screened against their root zones, the side corridor measured for machinery, and the slope read from state elevation data. This guide publishes each threshold, where it comes from, and the measurement error it carries until a surveyor replaces the satellite.
By Joey Don · Co-Founder & CEO, E2ES · Verified 3 November 2026 against the placement rules in code and the public mapping sources below
Short answer
A granny flat "fits" when one of three fixed footprints — 10.59 × 3.24 m (34 m²), 8.34 × 7.59 m (60 m²) or 9.99 × 8.64 m (80 m²) — can be placed whole behind the front wall of the house with 1 m to every side and rear fence, easement and shed (1.5 m to boundaries on a Queensland lot), 1.8 m to the house (1 m where the fire-rated short wall faces it), no structural root zone touched, a side corridor graded against 3.0 m for machinery, the fall across the lot reported in bands, and no mapped overlay that excludes the pathway. Every satellite distance carries about ±1 m until the survey, so a near miss is reported as a number — "rear depth short by 0.4 m" — not a verdict. Check an address to run it on your lot.
Who builds it, for how much, how long
Who builds this, and what to do next
E2ES builds small second dwellings (granny flats) in Melbourne, Geelong, Ballarat and Bendigo at Victorian fixed prices including GST — $121,000 (34 m²), $170,500 (60 m², two or three bedrooms), $218,900 (80 m²) — one fixed price, all in, on a programme of 4 weeks paperwork, then 3 months construction. 77 completed and leased E2ES dwellings across 21 suburbs are mapped with their weekly rents at /our-builds (74 in Victoria, 3 in Queensland; dataset refreshed 2026-08-27).
Next step: check an address, compare the floor plans, or book a free site assessment.
Price book updated 2026-10-17 · builder facts reviewed 2026-11-03
What the assessment starts from: title, easements, house footprint
The first inputs are not ours. The lot boundary and any easements come from the Vicmap cadastre (Land Use Victoria, CC BY 4.0), which is the state record of parcel geometry; the plan of subdivision and certificate of title are ordered to confirm them, because an easement that is on title but missing from the map still binds the land. We treat an empty easement result as "none found in the data", never as a clean title.
The existing house is taken from the best source available in this order: the state-mapped building footprint where one exists, otherwise an open building-footprint dataset, and in every case checked against current aerial imagery, from which the roof outline is detected and the wall line estimated by stepping the eave in about 0.45 m. Where the only source is the open dataset we have measured offsets of 1.4–3.4 m against the imagery, so the footprint is redrawn to the roof and labelled approximate.
The imagery itself has a known error. Satellite tiles are registered to the cadastre only where a state-mapped footprint anchors them; elsewhere the whole image can sit about ±1 m off the title boundary in a random direction. In our own check of 120 sites against agents' overhead photographs on 3 October 2026, the side-passage measurements were right on average (mean difference +0.03 m) but with a standard deviation of 1.12 m. That is why every distance on an assessment map is a screening figure, and why the surveyor's set-out, not the map, decides a build.
Three fixed footprints, placed whole — never stretched, never mirrored
We do not draw a blob and ask whether a house could go there. We place one of three real floor plans, at their built outer dimensions, and report whether that plan fits with every clearance intact. The plan may rotate to any angle to suit the yard; it is never stretched, rearranged or mirrored, so what fits on the map is the house that arrives on site.
Each plan is tried in two door orientations where the yard allows: scheme A with the entry facing the main house, scheme B with the entry facing the driveway side. We also draw a 1.8 m fence across the yard halfway between the house and the granny flat with a 1 m gate at the driveway end, because a separate tenancy wants a separate yard. None of that is a planning rule — it is the configuration most owners end up asking for.
The dimensions below are the published drawings' outer rectangles; the drawing areas on the floor-plan catalogue are the areas recorded on each supplied drawing, and neither is a statutory floor-area measurement under Clause 73.03.
The clearances: 1 m to fences, easements and sheds; 1.8 m to the house
The placement engine enforces the same clearances the building and fire rules will later require, so a position that passes the screen is a position a surveyor can usually work with. The granny flat sits behind the front wall of the existing house, at least 1 m from every side and rear boundary measured to the fence, at least 1 m from any easement, and at least 1 m from any shed or structure the aerial detection finds. On a Queensland lot the map planner applies the 1.5 m side and rear setback of QDC MP 1.2 instead of 1 m.
To the main house the default is 1.8 m, the National Construction Code's separation between Class 1 buildings on the same lot. Our standard modules ship with a fire-rated short wall — the 3.24 m end of the 34 m² home, the shorter face of the 60 m² home — so when that face is the one toward the house, 1 m is enough and the engine knows it. Where the long face must turn to the house, 1.8 m is kept.
If the plan does not fit with the existing sheds in place, the engine tries again with the sheds removed, and then with the sheds removed and the trees cleared, and reports which of the three it needed. A "fits after the shed goes" result is drawn in a different colour on the map and said in words on the card; it is not presented as a clean fit.
Send the address. We run every test above and tell you the numbers, not just the verdict.
The free site assessment places the 34, 60 and 80 m² homes behind your house on the state cadastre and current imagery, reports every clearance, the trees, the corridor, the slope and the overlays, and names the next step for each.
Trees: three root-zone bands, not a guess
Trees are the item most likely to change between the map and the site visit, so the screen does not pretend to know more than it does. The aerial detection estimates each tree's canopy, and from it the structural root zone and the nominated root zone in the manner of AS 4970:2025. Any encroachment on the structural root zone rejects the position. Encroachment on the nominated root zone of 10 per cent or less is treated as minor; 10–20 per cent returns a conditional result that needs an arborist's review before anyone relies on it; above 20 per cent the position is rejected.
Whether a tree can be removed at all is a separate question that the screen cannot answer: a Vegetation Protection Overlay, a Significant Landscape Overlay or a local tree law may require a permit, and the assessment says so where an overlay is present rather than assuming the tree can go.
Getting it in: the 3 m corridor, and what a narrow side means
A granny flat that fits in the yard still has to reach it. The screen measures the widest side passage from the house wall to the fence at 0.5 m intervals and grades it: 3.0 m or more is the corridor the delivery and site machinery need and is marked green; a passage that only allows a person to walk — 0.9 m — is marked red for machinery; between the two is a yellow result that depends on what is in the way and whether a crane position exists from the street or a neighbour. The corridor is also where every service connection will run.
Because the passage is the measurement most exposed to the ±1 m imagery error, the screen is deliberately conservative about it. A measured corridor between 2.6 and 3.0 m is reported as "needs a site check", not as a fail and not as a pass; a corner lot with a second street frontage is reported as having an alternative access; and where an agent's overhead photograph of the lot exists, we measure the passage in that photograph as well and only ever use it to downgrade a result, never to upgrade one.
Slope: read in bands, never used to refuse
The fall across the lot is read from state elevation data — a numeric terrain model where it is available, contour lines where it is not — and reported in bands rather than as a verdict. A fall of 1 m or less across the parcel is treated as flat. Falls of 1–2 m, 2–3 m and more than 3 m are reported as such, because each band changes what the slab, the drainage and the access path will cost, not whether the project is possible. Where the elevation data cannot be read reliably the assessment says "terrain not confirmed" and does not assume flat.
Across the side passage the screen separately flags a gradient steeper than 1 in 14 — the Building Regulations' access-path limit (reg 86B) — which is the point at which a level access path and the machinery corridor both need design attention.
Overlays and the planning pathway: checked, not assumed
Zone and overlays are read for the parcel from the Vicmap planning layers, sampling inside the boundary so that a neighbour's overlay touching the fence is not counted as yours. The small second dwelling pathway in Clause 73.03 and the zone tables is summarised on our Victorian rules guide; the screen reports whether the zone is one in which that pathway can apply and lists every overlay on the parcel with its effect, from "no planning trigger" through "may add a condition" to "a permit is required" and "normally excluded". A Floodway Overlay, for example, is treated as excluding; a Vegetation Protection Overlay is a condition on tree removal, not on the dwelling.
What the screen cannot read is the title: a restrictive covenant or a Section 173 agreement can stop a second dwelling on a lot that passes every mapped test, which is why the title-level guide sits beside this one and why the documents are ordered before design money is spent.
What the result means, and what it does not
An assessment that says a plan fits means: on the state cadastre, the detected house and the current imagery, this plan at its built dimensions can be placed behind the house with the clearances above, the trees screened as described, the corridor and slope reported as described, and no mapped overlay that excludes the pathway. It does not mean the position has been surveyed, that an easement authority has consented, that an arborist has signed off a tree, that the covenant has been read, or that a building permit will issue. Each of those is a named next step on the result, and the written proposal that follows prices them.
An assessment that says a plan does not fit says which clearance it could not keep and by how much — "rear depth short by 0.4 m", "side passage 2.55 m against 3.0 m" — because a near miss on the satellite is exactly the case a site visit resolves. We would rather tell you the number than the verdict.
Primary sources
- Vicmap — Victorian spatial data catalogue (Land Use Victoria)The state cadastre the assessment reads for lot boundaries, easements and planning layers; CC BY 4.0.
- Building Regulations 2018 (Vic), authorised version 031Reg 74A (behind the front wall of the existing dwelling); reg 79 and Table 79 (side and rear setback 1 m for walls up to 3.6 m); reg 86B (access path at least 1 m wide, gradient no steeper than 1:14).
- NCC 2022 Volume Two H3D3; Housing Provisions Part 9.2 — fire separation of external wallsA Class 1a wall within 1.8 m of another dwelling on the lot needs fire-resisting construction — the reason for the 1.8 m default and the 1 m fire-rated short face.
- Water Act 1989 (Vic) s 148 — structures over works and easementsNo structure over a water authority easement or within 1 m laterally of its works (5 m for Melbourne Water) without consent — the 1 m easement clearance.
- Melbourne Water — apply to build near an asset or easementConsent process for building over or within 5 m of Melbourne Water easements or underground assets.
- Victoria Planning Provisions — ordinance (Clause 54 Standard A2-8, Clause 73.03)The "behind the front wall" siting standard the planner mirrors, and the small second dwelling definition summarised on the planning update page.
- Queensland Development Code MP 1.2 (lots 450 m² and over)The 1.5 m side and rear setback for walls up to 4.5 m mean height that the map planner applies on a Queensland lot.
- Standards Australia — AS 4970:2025 Protection of trees on development sitesThe structural root zone and tree protection zone method the tree screen follows.
- E2ES — Australian granny flat rules dataset (CC BY 4.0)The siting rows (reg 74A, 79, 76, 77, 86A, 86B) and overlay effects the assessment applies, as machine-readable JSON.
Frequently asked questions
It depends on four distances, and the assessment measures all of them: the 60 m² home is an 8.34 × 7.59 m rectangle that must sit behind the front wall of your house, at least 1 m from every side and rear fence and from any easement or shed, and 1.8 m from the house (1 m where its fire-rated short wall faces the house). The plan rotates to find a position but is never shrunk. In most yards we have seen, a rear depth of about 10 m behind the house with no easement in the way is where a comfortable fit begins; the result tells you the exact shortfall if there is one.
We place every plan at least 1 m from side and rear boundaries, measured to the fence line, which matches the 1 m side and rear setback the Building Regulations 2018 (reg 79) apply to walls up to 3.6 m high on a lot; on a Queensland lot the map planner uses 1.5 m (QDC MP 1.2). A surveyor confirms the boundary on site — the satellite map can be about ±1 m out — so a position that only just clears 1 m on the screen is reported as needing a site check.
Not without the consent of the authority the easement protects, and for a habitable building that consent is harder to obtain than for a shed. The screen keeps the plan at least 1 m clear of any mapped easement and labels the distance; where the only fitting position would cross one, it says so rather than assuming consent. Re-siting clear of the strip is usually the practical answer.
The aerial detection estimates each tree's root zones: any encroachment on the structural root zone rejects a position; up to 10 per cent of the nominated root zone is treated as minor, 10–20 per cent needs an arborist's review before the position is relied on, and more than 20 per cent is rejected. Whether a tree may be removed is a separate planning question — a Vegetation Protection Overlay or local law may require a permit — and the assessment flags that rather than assuming the tree can go.
For delivery and site machinery, a clear corridor of 3.0 m from the house wall to the fence is the green result; 0.9 m is enough for a person but not for machinery. Between 2.6 and 3.0 m sits inside the imagery error band and is reported as needing a site check. A corner lot with a second frontage, or a crane position from the street, can change the answer, and the result says when either applies.
Good enough to screen, not to build from. Imagery is only registered to the title boundary where a state-mapped house footprint anchors it; elsewhere it can sit about ±1 m off in a random direction. In our own 120-site check against overhead photographs on 3 October 2026 the side-passage measurements averaged within 0.03 m of the photograph but with a 1.12 m standard deviation. The surveyor's set-out replaces every map distance before anything is poured.
Slope is reported in bands, not used to refuse: a fall of 1 m or less across the lot is treated as flat; 1–2 m, 2–3 m and more than 3 m are reported so the slab, drainage and access can be priced in the proposal. A side passage steeper than 1 in 14 is separately flagged for the access path. Where elevation data cannot be read the assessment says so rather than assuming flat ground.
No. It means the plan at its built dimensions can be placed on the mapped lot with the clearances kept and no mapped overlay that excludes the pathway. Survey, easement consent, arborist sign-off, the covenant on title and the building permit are each named next steps on the result, and the written proposal prices them. The current Victorian planning rule for small second dwellings is summarised on our rules guide at /small-second-dwelling-victoria.
Read next
Check an address now
The instant Victorian screen — zone, overlays and lot size — and the site feasibility report for VIC, QLD, NSW and WA addresses.
Map planner — VIC + QLD
Your real lot, easements and buildable zone; drag a 30 or 60 m² unit into place with the 1 m (VIC) or 1.5 m (QLD) setback applied.
The three footprints as drawings
Seven supplied drawings, drawing areas and the state prices including GST.
Easements and covenants
The title-level checks the map cannot read: build-over consent, restrictive covenants, Section 173 agreements.
Victoria's small second dwelling rules
The current 80 m² planning definition (VC306), the lot and zone conditions, and the building-permit caveat.
Important information
The assessment is an automated screen of public mapping and current imagery. It does not involve a site measurement, a title search unless one is ordered, an engineering or arborist inspection, or any approval, and it makes no assurance of buildability, approval or cost. Distances carry an error of about ±1 m until confirmed by survey. Whether a particular lot, easement, tree or covenant permits a second dwelling turns on documents and site conditions the screen cannot read; nothing on this page is planning, building or legal advice.
Send the address. We run every test above and tell you the numbers, not just the verdict.
The free site assessment places the 34, 60 and 80 m² homes behind your house on the state cadastre and current imagery, reports every clearance, the trees, the corridor, the slope and the overlays, and names the next step for each.
Free Site Assessment
Start with a
30-minute site visit.
Tell us your address and the layout you have in mind. We’ll review council overlays and site requirements, then discuss your design, scope and quote. No obligation.
Sales & Feasibility
+61 480 099 909
enquiries@e2es.com.au
Office
Suite 631, Waterman Workspace, 44 Lakeview Drive, Scoresby VIC 3179